SP Power Cable EW1-

North Buona Vista (Permanent Shaft) &

Ayer Rajah (Permanent Shaft)

Project:
SP Cable EW1
Client:
Singapore Power
Main Contractor:
Obayashi Corporation
Contract Duration:
Jul 2013 to Oct 2016

Description:

Construction of 2 East West Transmission Cable tunnel, include Drilling for blasting, Rock Bolt and Shotcreting and Permanent Lining Works in the Shafts, Adit and Enlargements for the Project, at Ayer Rajah Shaft, North Buona Vista Shaft and Holland Shaft
PROJECT PAGE FILL hor

Jurong Rock Cavern Project

( 2 shafts dia 24m, Depth 132m)

Project:
Jurong Rock Cavern
Client:
Jurong Town Corporation
Main Contractor:
Sato Kogyo (S) Pte Ltd
Contract Duration:
Jul 2007 to Jun 2009

Description:

Construction of two 24.0 m diameter shafts to a depth of 132m using explosive and non-explosive methods.

PROJECT PAGE FILL

LTA MRT Circle Line C902

Pipe Roof & NATM Tunnel Project

Project:
Downtown line 1 C902 @ Promenade Station
Client:
Land Transport Authority
Main Contractor:
Shanghai Tunnel Engineering Co. Ltd
Contract Duration:
Jul 2010 to Nov 2011

Description:

Installation of Pipe Roof and construction of 2 NATM Tunnels.

PROJECT PAGE FILL

LTA MRT Downtown Line2

C915-Cut & Cover Station project

Project:
Downtown line 2 C915 @ Hillview Station
Client:
Land Transport Authority
Main Contractor:
SK E&C Co. Ltd
Contract Duration:
Nov 2011 to Oct 2014

Description:

Construction of cut & cover station box permanent works of tunnels between Station @ Beauty World and Hillview.

PROJECT PAGE FILL

LTA MRT Downdown Line

C918-Cross Passage & Sump Pit Project

Project:
Downtown line 2 C918A @ Tan Kah Kee Station
Client:
Land Transport Authority
Main Contractor:
SK E&C Co. Ltd
Contract Duration:
Jan 2014 to Sep 2014

Description:

Construction of 34m long Cross passage and 2 pump sumps include both temporary and permanent works.

PROJECT PAGE FILL

LTA Thomson Line Advance Work

T2123-NATM Tunnel & Pile removal

Project

Project:
Thomson Line Advance work T2123
Client:
Land Transport Authority
Main Contractor:
Presscrete Engineering Pte Ltd
Contract Duration:
Nov 2014 (On Going)

Description:

Construction of 142m long NATM tunnel, removed piles and I beams. Complete and finish with LSS back filling.

PROJECT PAGE FILL

PUB Deep Tunnel Sewerage System T0-1

Project:
PUB-DTSS T0-1
Client:
Public Utilities Board
main Contractor:
Woh Hup, Shanghai Tunnel EC JV
Contract Duration:
Apr 2000 to Apr 2005

Description:

Construction of Work Shaft and NATM tunnel. Concrete Permanent Lining Construction

PROJECT PAGE FILL

Deep Tunnel Sewerage System (DTSS)

Phase 2 Project

Project:
DTSS – Phase 2 (T07)
Client:
Public Utilities Board
Main Contractor:
Ed. Zublin AG, Singapore Branch

Contract Duration:
Jan 2019 (Ongoing)

Description:

 

 

TEL Springleaf Station Project

Project:
Thomson-East Coast Line T208 @ Springleaf Station
Client:
Land Transport Authority
Main Contractor:
Leighton & John Holland JV

Contract Duration:
Sep 2016 – Oct 2017

Description:

Construction of 6 nos of Cross Passages and 3 nos of Sump Pit

PROJECT PAGE FILL

Changi Jewel Project

Project:
Jewel Changi Airport
Client:
Jewel Changi Airport Trustee Pte Ltd
Main Contractor:
Woh Hup & Obayashi JV

Contract Duration:
Jul 2016 to Jul 2018 

Description:

Shotcrete Works

PROJECT PAGE FILL

T222 Project

Project:
T222
Client:
Land Transport Authority
Main Contractor:
Daelim Industrial Co. Ltd

Contract Duration:
Jan 2017 – 

Description:

Shotcrete Works

PROJECT PAGE FILL

T219 Project

Project:
T219
Client:
Land Transport Authority
Main Contractor:
Penta Ocean & Bachy JV

Contract Duration:
Aug 2017 – 

Description:

Construction of Mined Tunnel. 

PROJECT PAGE FILL

DTL3 Tampines East Station Project

Project:
Downtown Line 3 C925 @ Tampines East Station
Client:
Land Transport Authority
Main Contractor:
GS Engineering & Construction Crop

Contract Duration:
Jan 2016 to Nov 2016

Description:

Construction of 2 nos of Mined Tunnel & Reinforced Concrete works at Entrance C & D.

PROJECT PAGE FILL

TEL Havelock Station Project

Project:
Thomson-East Coast Line T221 @ Havelock Station
Client:
Land Transport Authority
Main Contractor:
China Railway Tunnel Group

Contract Duration:
Feb 2017 to May 2017

Description:

Cast Insitu Tunnel Lining and Double Base Slab.

PROJECT PAGE FILL

TEL Woodlands North Station Project

Project:
Thomson-East Coast Line T202 @ Woodlands North Station
Client:
Land Transport Authority
Main Contractor:
Penta Ocean Construction Co Ltd

Contract Duration:
Apr 2017 – Jun 2017

Description:

Cast Insitu Tunnel Lining.

PROJECT PAGE FILL

TEL Orchard Station Project

Project:
Thomson-East Coast Line T219 @ Orchard Station
Client:
Land Transport Authority
Main Contractor:
Penta Ocean Construction Co Ltd & Bachy Soletanche JV

Contract Duration:
May 2017 to Mar 2018

Description:

Construction of 1 nos of Sump Pit. 

Contract Duration:
Aug 2017 to Jan 2018

Description:

Construction of 1 nos of Mined Tunnel (63m in Length). 

PROJECT PAGE FILL

TEL Brighthill Station Project

Project:
Thomson-East Coast Line T211 @ Brighthill Station
Client:
Land Transport Authority
Main Contractor:
Penta Ocean Construction Co Ltd

Contract Duration:
Sep 2017 – Nov 2017

Description:

Tunnel Enlargement.

PROJECT PAGE FILL

TEL Upper Thomson Station Project

Project:
Thomson-East Coast Line T212 @ Upper Thomson Station
Client:
Land Transport Authority
Main Contractor:
Sato Kogyo (S) Pte.Ltd

Contract Duration:
Oct 2017 – Apr 2018

Description:

Construction of 2 nos of Cross Passages. 

Contract Duration:
May 2018 – Oct 2018

Description:

Bracket Installation @ TBM2. 

PROJECT PAGE FILL

TEL Lentor Station Project

Project:
Thomson-East Coast Line T209 @ Lentor Station
Client:
Land Transport Authority
Main Contractor:
China Railway No.5 Engineering Group Co.Ltd

Contract Duration:
Dec 2017 – Jan 2018

Description:

Construction of 2 nos of Cross Passages. 


facebook like buttonContact Us